Webber Elementary
Webber Architect Presentation (Oct. 9, 2019)
Photo Progress
- August 17, 2021
- August 10, 2021
- August 4, 2021
- July 27, 2021
- July 19, 2021
- July 14, 2021
- July 6, 2021
- June 22, 2021
- June 15, 2021
- June 8, 2021
- June 2, 2021
- May 25
- May 19
- May 11
- May 4
- April 28
- April 27
- April 20
- April 14
- April 6
- March 30
- March 23
- March 15 -- Tour
- March 9
- March 2
- January 27
- January 19
- January 12
- January 5
- December 29
- December 22
- December 15
- December 8
- December 2
- November 17
- November 4
- October 13
- September 22
- September 15
- September 1
- August 26
- July 14
- July 1
- June 26
- June 2
August 17, 2021
August 10, 2021
August 4, 2021
July 27, 2021
July 19, 2021
July 14, 2021
July 6, 2021
June 22, 2021
June 15, 2021
June 8, 2021
June 2, 2021
May 25
May 19
May 11
May 4
April 28
April 27
April 20
April 14
April 6
March 30
March 23
March 15 -- Tour
March 9
March 2
January 27
January 19
January 12
January 5
December 29
December 22
December 15
December 8
December 2
November 17
November 4
October 13
September 22
September 15
September 1
August 26
July 14
July 1
June 26
June 2
Moose Tree Center
Plans
A design team is working to create a replacement academic wing of the building, plus a reconstructed office including a secure entrance, a new STEM lab, and a new media center.
The site will also have redesigned parking for improved traffic flow, including a new bus loop.
Students will remain in the current facility during construction of the new wing. Once the new wing is completed, students will move into that area, allowing the previous wing to be removed.
The construction is expected to begin in the spring of 2020 and conclude in the fall of 2021.
Process
The new wing, along with the secure entrance, was completed and opened in the fall of 2021.