Webber Elementary
Webber Architect Presentation (Oct. 9, 2019)
Photo Progress
- March 2
- January 27
- January 19
- January 12
- January 5
- December 29
- December 22
- December 15
- December 8
- December 2
- November 17
- November 4
- October 13
- September 22
- September 15
- September 1
- August 26
- July 14
- July 1
- June 26
- June 2
March 2
January 27
January 19
January 12
January 5
December 29
December 22
December 15
December 8
December 2
November 17
November 4
October 13
September 22
September 15
September 1
August 26
July 14
July 1
June 26
June 2
Moose Tree Center
Plans
A design team is working to create a replacement academic wing of the building, plus a reconstructed office including a secure entrance, a new STEM lab, and a new media center.
The site will also have redesigned parking for improved traffic flow, including a new bus loop.
Students will remain in the current facility during construction of the new wing. Once the new wing is completed, students will move into that area, allowing the previous wing to be removed.
The construction is expected to begin in the spring of 2020 and conclude in the fall of 2021.
Process
Construction continues on the site.
The renovated office and secure entry are now completed and available as is the new playground.
The foundation has been laid for the addition behind the school and will continue to be built out over the winter. (December 1, 2020)