Bond Project Sequencing Principles

Compliance with approved Treasury application

  • Michigan Department of Treasury and Audit oversight
  • Project integrity
  • Legal compliance

Immediate need

  • Safety and security
  • Educational programming
  • Wired and Wireless Network Infrastructure upgrade

Financial Planning

  • Contractors/Vendor availability
  • Economies of Scale (Orion Oaks/ECC concurrent projects)
  • Bid timing

Equity by level (HS, MS, Elementary)

  • Secure entrances
  • Educational impact
  • Furnishings

Logical sequencing within and between projects

  • NOTA -> Blanche Sims
  • Early Childhood Center -> CERC
  • Useful life (technology, facilities, etc.)

Professional experience/expertise

  • Architect
  • Construction Manager
  • Technology designer