Bond Project Sequencing Principles
Compliance with approved Treasury application
- Michigan Department of Treasury and Audit oversight
- Project integrity
- Legal compliance
Immediate need
- Safety and security
- Educational programming
- Wired and Wireless Network Infrastructure upgrade
Financial Planning
- Contractors/Vendor availability
- Economies of Scale (Orion Oaks/ECC concurrent projects)
- Bid timing
Equity by level (HS, MS, Elementary)
- Secure entrances
- Educational impact
- Furnishings
Logical sequencing within and between projects
- NOTA -> Blanche Sims
- Early Childhood Center -> CERC
- Useful life (technology, facilities, etc.)
Professional experience/expertise
- Architect
- Construction Manager
- Technology designer